Saturday 4 October 2014

Heating: Ground floor - Insulation and pipes

With all the 1st fix plumbing and electrics in place, we were able to start work on the heating system. We had chosen to use underfloor heating for both the ground and first floors, though each floor would require slightly different methods of installation.

For the ground floor, the first step was to lay sheets of insulation through the whole house.





Nowadays, building regulations require quite a lot of insulation to be placed under the floor, especially when using underfloor heating as this helps prevent the heat from being lost through the ground.





Before we could start laying the insulation, we had to do some preparation for the liquid screed. Alan built some mini-partitions between some of the internal wall studwork which would prevent the liquid screed from flowing into the wall cavities.







This type of insulation is expensive. To save on wastage, Alan worked out exactly how much insulation we would need and even drew up a 'jigsaw-piece' plan that utilised all the off-cuts.





More prep. Alan used a hammer drill and angle grinder to cut away the dolly blocks in the doorways. Now you see them...





... now you don't.
The blocks needed to be removed as there would be underfloor heating pipes running through the doorways.





The first sheet of insulation is laid. Only another 74 square metres to go!





Pipes and wires running on the concrete floor were a bit tricky. This conduit carried the cooker wire from the wall to the kitchen island, so we cut a groove in the insulation to fit.





Final check to make sure everything lines up...





...it does. Hooray! That's the kitchen finished.





The study is nearly done and waiting for its designated off-cuts from another room.





The lounge is finished.





Removing the dolly blocks from around the front and side doors proved to be a bit more involved. Alan had to re-jig some of the door frame supports in order to get the blocks out. He also had to be very careful not to damage the paintwork on the new doors themselves.





With the blocks gone, the floor is ready for insulation.









The site inspector appreciated the increase in floor height as it allowed him to see out of the front door.





The downstairs toilet was particularly awkward because it contained four sets of pipes to contend with.







What a nuisance! This piece took some carving, but was a good fit... eventually. Bah!





Alan's plan worked really well and we finished laying the insulation with barely any waste. Though the insulation was tightly fitted through every room, I taped all the joints with duct tape to ensure that there was no chance of any movement.







The liquid screed would be pumped in on top of the insulation so we needed to ensure that every room was a watertight tub. To achieve this, we laid out heavy gauge polythene sheeting.  







A yellow foam strip was attached around the perimeter of each room to allow for the screed to expand and contract while it dries.







The underfloor heating pipes waiting to be unwrapped and installed.







The pipe laying begins. We had a set of plans to work from so it was relatively straightforward to unroll and clip down each circuit.





As our system will be powered by a heat pump (rather than a traditional boiler) the pipes were designed to be laid close together. This meant that we had to be careful not to kink the pipes when bending the loops.





Alan cut measured lengths of batten to use as a gauge so the pipes were equally spaced. In the kitchen, we left spaces for the kitchen cabinets and the island as there was no point heating under those areas.





Each zone uses a complete, unbroken length of pipe that stretches from the manifold, looping through a room and then back to the manifold again.







Where pipes crossed a door threshold we created 'movement joints' by using conduit sleeves. These help prevent any cracks appearing later in the screed.







All roads pipes lead to Rome manifold.







As this was our first time installing underfloor heating and considering the grave consequences if it should go wrong after the concrete screed had been poured, we felt it best to get a plumber in for a few hours to help set up the manifold and pressure test the system.





Our ground floor heating plan up on the wall for reference.





As you can see from these pictures, the site inspector was absolutely ecstatic with our progress.





No comments :